ACCA每日一小考 8-22
Capacity levels used in setting standard absorption rates for production overheads are often related to performance standards. To which performance standard is budgeted capacity often associated?

A. Ideal standard.
B. Basic standard.
C. Current standard.
D. Attainable standard.

正确答案:C


答案解析:


The correct answer is: Current standard.


Budgeted capacity is associated with current standards.

Budgeted capacity is not associated with basic standards.

Practical capacity is associated with attainable standards.

Full capacity is associated with ideal standards.

您需要登录后才可以回帖 登录 | 立即注册

本版积分规则

小黑屋|ACCA论坛,ACCA考友论坛-全球ACCA中文论坛|中国ACCA学习网

GMT+8, 2024-11-5 18:54 , Processed in 0.087457 second(s), 27 queries .

Powered by Discuz! X3.4

Copyright © 2001-2021, Tencent Cloud.

快速回复 返回顶部 返回列表